Timeline - Phase Two instruments project

The four new instruments in this project will be built over a period of four years from 2010-2013.

 

2010

 

Project start

April 2010

Start instrument engineering design

April 2010

Start phase two instrument moderator engineering design

April 2010

2011

 

Start Chipir instrument installation

April 2011

Commissioning of Phase Two moderators complete

August 2011

Start Larmor installation

May 2011

Start Zoom installation

October 2011

2012

 

First beam Chipir instrument

April 2012

First beam Larmor instrument

August 2012

Start Imat installation

March 2012

2013

 

First beam Zoom instrument

March 2013

First beam Imat instrument

March 2013

Project complete

September 2013