Dateno. DaysRB no.PISample EnvironmentLocal Contact
Tue 05/07/112CalibrationIRISCCR/TL/HeGarcía Sakai
Thu 07/07/1161110399KrzystyniakCCR/TL/HeFernández Alonso
Wed 13/07/111ReserveKrzystyniakCCR/TL/HeFernández Alonso
Thu 14/07/111TBD   
Fri 15/07/1131120210ClarkeCCR/TL/HeGarcía Sakai
Mon 18/07/111BEAM OFF   
Tue 19/07/1121120210ClarkeCCR/TL/HeGarcía Sakai
Thu 21/07/111ReserveClarkeCCR/TL/HeGarcía Sakai
Fri 22/07/1151120490ThompsonCCR/TL/HeGarcía Sakai
Wed 27/07/111ReserveThompsonCCR/TL/HeGarcía Sakai
Thu 28/07/1171120198YamamuroCCR/TL/HeGarcía Sakai
Thu 04/08/111ReserveYamamuroCCR/TL/HeGarcía Sakai