Inter Timeline
05 Aug 2009
Yes
-  

 

No
No
 
No
No
 

 

No
 

2002

 
First Science and Technical Advisory Committee July 2002

2003

 
Detailed planning approval March 2003
Approve initial instrument suite June 2003
Approve target station design concept July 2003
First project board October 2003
Complete earth moving and landscaping November 2003

2004

 
Complete access road 10 October 2004
Complete R78 technical support building November 2004

2005

 
Begin R80 experimental hall construction January 2005
Complete R80 structural frame May 2005
Complete target monolith foundation September 2005
R80 weather-tight November 2005

2006

 
Complete R80 construction March 2006

2007

 
Complete target services area structure January 2007
Begin extracted proton beam installation in synchrotron February 2007
Complete target services area equipment December 2007
Complete target station December 2007
Complete extracted proton beam September 2007
First proton beam to target area December 2007

2008

 
Begin instrument neutron guides January 2008
Begin first phase instrument detectors March 2008
Begin instrument commissioning July 2008
First complete instrument installation July 2008
First measurable neutrons from target July 2008
Target core fully operational July 2008
Start of experimental programme October 2008
Contact: